What the variations pathway means for certifiers: the 10-day council clock

If the proposed CDC variation pathway goes ahead, private certifiers get a new step in the middle of their assessment: referring a near miss to council, which has 10 days to decide or the variation is deemed approved. Here's how that would change your workflow, and the questions still open.

Updated 9 October 20263 min readNSW
Two professionals reviewing printed documents with a laptop on the table
Status at 9 October 2026: proposed, not law. Exhibited 14 May to 24 June 2026 and listed as "under consideration". Details may change in the final instrument.
In short
  • You'd refer a variation to council. Council has 10 calendar days to decide, or it's deemed approved.
  • If deemed approved, you can keep assessing the rest of the standards and issue the CDC.
  • Cap: 3 to 4 standards per development, counting the original CDC and any later modifications.
  • Councils, through LGNSW, want longer timeframes, no deemed approval and a cap of two.

Your workflow, before and after

StepTodayUnder the proposal
Design misses one standardRefuse, or applicant redesigns or goes to a DAIf it's a variable standard, refer to council for a variation certificate
Council's roleNoneDecides the variation only, within 10 days
Council doesn't decide in timen/aDeemed approved; you continue
Who issues the CDCYouStill you, once the variation is approved or deemed approved
Applicant's extra costn/a$342 to $569 per variation certificate, depending on the fee option chosen

The 10-day clock

Councils would get 10 calendar days to assess a variation when a private certifier refers it, and 20 calendar days when council assesses both the variation and the CDC. Miss the deadline and the variation is deemed approved.

For certifiers, that's predictable: a worst case of 10 days added, not 60+. But it raises practical questions you'll want answered in the final rules:

  • When does the clock start? On referral, or when council accepts the referral as complete?
  • Can council stop the clock by asking for more information?
  • How is a deemed approval recorded on the Planning Portal, so you have evidence on file?
Person writing notes beside a laptop at a desk
Every variation will need a clear paper trail.

The "3 to 4 variations" cap

The department proposes that no more than 3 to 4 standards can be varied for a single development, and the limit covers the original CDC plus any later modifications.

Open questions:

  • Three or four? The exhibited material gives a range, not a number.
  • What counts as one variation? Is a side setback that fails on both sides one variation or two?
  • Modifications: if two variations are used at CDC stage, the applicant only has one or two left for any later change. That needs managing from day one.

Split approvals and who's responsible

Under the proposal, you'd issue the CDC while council approved the variation inside it. LGNSW warns that neighbours will see it as one approval and won't know who to complain to. It asks for clear public information about who decided what.

For certifiers, the practical point is record keeping: the variation certificate (or the evidence of deemed approval) becomes part of the basis for your CDC. Keep it with the file.

What councils want changed

Local Government NSW's submission pushes back on several points:

IssueProposedLGNSW wants
Timeframe10 calendar days (20 if council does the CDC)15 working days (25 if council does both)
Deemed approvalYesRemoved entirely
Cap3 to 4 standards2 standards; more should be a DA
Fees$342 to $569Full cost recovery, set with councils
Subjective testse.g. garage "not visually dominant"Every variable standard should be measurable

How much of this survives into the final rules isn't known yet.

Getting ready

  1. Know the variable standards. Height, floor area, setbacks, articulation zone, privacy screens, garage doors and a few more. See the explainer.
  2. Tell clients early how many variations they're using, so they don't run out at modification stage.
  3. Budget the extra 10 days into quoted timeframes for jobs that need a variation.
  4. Watch for the final instrument and the Planning Portal changes that will come with it.

Check your design in a minute

Enter your lot size and building dimensions. The free quick check tests height, storeys, setbacks and landscaped area against the Housing Code, clause by clause. No account needed.

Sources

  1. NSW Planning Portal, Summary of EIE: Variations and changes to complying development (May 2026).
  2. NSW Planning Portal, Variations and changes to complying development: Explanation of Intended Effect (under consideration; cap, fees, transitional rule). Checked 9 October 2026.
  3. Local Government NSW, Submission on Variations and Changes to Complying Development EIE (2026).
  4. SN Architects, Close enough to complying.

General information only, current at 9 October 2026. It is not legal, planning or certifier advice. Confirm with a registered certifier or your council.